Which configuration baseline provides the details from which a contractor can transition from design to production?

Explanation:
In configuration management, baselines lock in a specific configuration at a point in time so everyone has a common reference. The one that enables moving from design to manufacturing is the product baseline. It contains the approved, actual configuration of the item—everything from the bill of materials and drawings to the interfaces and implemented design. This is the point where the design is ready to be reproduced in production, so manufacturers know exactly what to build and how to assemble it. The other baselines describe different aspects: a functional baseline captures the functions and performance the system must provide, an allocated baseline shows how those requirements are distributed to components, and a performance baseline specifies expected performance characteristics. They guide design and verification, but they don’t authorize or define the exact product to be produced. Therefore, the product baseline is the appropriate reference for transitioning to production.

In configuration management, baselines lock in a specific configuration at a point in time so everyone has a common reference. The one that enables moving from design to manufacturing is the product baseline. It contains the approved, actual configuration of the item—everything from the bill of materials and drawings to the interfaces and implemented design. This is the point where the design is ready to be reproduced in production, so manufacturers know exactly what to build and how to assemble it.

The other baselines describe different aspects: a functional baseline captures the functions and performance the system must provide, an allocated baseline shows how those requirements are distributed to components, and a performance baseline specifies expected performance characteristics. They guide design and verification, but they don’t authorize or define the exact product to be produced. Therefore, the product baseline is the appropriate reference for transitioning to production.